Level Crossing will be closed for TWO WEEKS
On the 12th September, road works begin at the level crossing at Freshfield Train Station on Victoria Road. The works will carry on for two weeks for which time the crossing will remain completely closed to traffic from the junction of Golf Road until 27th September.
SP Energy Networks are responsible for the works which consist of, "Construction of launch and Reception Pits and associated Duct work for installation of Ducts beneath Level Crossing by means of Directional Drilling".
There will also be Multi-Way Traffic Lights in place on the junction of Victoria Road and Freshfield Road from 12th September to 27th September due to Construction of launch and Reception Pits and associated Duct work for installation of Ducts.
Multi-Way Traffic Lights will also be in place on the junction of Victoria Road and Montagu Road for the same duration of 12th September to 27th September for traffic signals only, no excavation for works associated with Construction of launch and Reception Pits on Victoria Road/Freshfield Road.